Project Details

CFEnergía

Power generation with temporary mobile units

Ensure a reliable supply of 100 MW for Baja California during the summer peak demand period.

July – September 2025
Tijuana, Baja California

Project Context and Scope

During the peak summer demand in northwest Mexico, PYE Electrificaciones deployed and commissioned a temporary power generation system for CFEnergía, ensuring a reliable supply of 100 MW. The project was executed in a record time of 60 days, combining advanced engineering, high-level operational coordination, and strict quality and safety standards.

The solution included the design, construction, installation, and operation of a temporary generation plant equipped with FT8 MOBILEPAC aeroderivative gas turbines, strategically interconnected to the Herradura Substation and the existing natural gas network, ensuring safe and efficient integration into the regional power system.

Technical and Operational Requirements:

  • 100 MW generation capacity with high availability and immediate response.
  • Full infrastructure deployment in a maximum of 60 days.
  • Strict compliance with CFE, CENACE, and environmental regulations.
  • Safe, efficient, and removable without impacting permanent infrastructure.

Execution and Challenges

The scale of the project required precise planning and coordinated execution among multidisciplinary teams. Each phase was carried out under strict safety, quality, and compliance protocols, ensuring deadlines and technical requirements were met without compromising system reliability.

  • 1
    Adaptation of an elevating substation and construction of a 5.8 km overhead transmission line with 115 kV insulation, wooden poles, and 795 ACSR conductor.
  • 2
    Installation of six FT8 MOBILEPAC mobile units with fast-start capability and high efficiency.
  • 3
    Safe connection to the natural gas network, testing, and commissioning in record time.

Keys to Success: Time, Effectiveness, and Reliability:

  • Record timeline: Delivery of a turnkey solution —from design to operation— in only 60 days, ensuring supply ahead of peak demand.
  • Operational effectiveness: Sustained generation of 100 MW during the critical period, exceeding initial objectives through the strategic deployment of high-availability units.
  • System reliability: Secure integration with electrical and gas infrastructure, continuous monitoring, and uninterrupted operation.

Results and Impact:

This project marks a key milestone in Baja California’s energy security, strengthening the stability of the regional grid and reducing the risk of power outages. It also demonstrates PYE Electrificaciones capability to deliver robust temporary power solutions in critical scenarios, integrating technological innovation and operational excellence.

  • Reliable supply of 100 MW during peak demand.

  • Reinforced stability of the regional electrical system.

  • Efficient operation with continuous monitoring and control of critical parameters.